Internet World's Fair - Amended EO - 12979-00100/ID124608
bullet bullet bullet bullet

Attached is the Amended Engineering order for this network. This in conjunction with some more detailed information which John stewart will supply on the BIPP side should be used as the official transition documentation for all operations/customer service groups.

Latest status is as follows:

1/ 24 hr. ETE test WTN/Tokyo is in process and if all goes well will be completed 1/12.

2/ MCI equipment collocation at WTN is complete as of 1/11.

3/ Customer equipment install at WTN is now rescheduled for 1/17/95. This will include both the Customer router still not onsite and the remaining MFS installation.

Pending no further delays due to weather conditions here in the Northeast, we hope to be able to follow the above schedule over the next week.

Regards, Nancy

Forwarded message: _________________________________________________________________ Date: Fri Jan 12, 1996 10:42 am EST From: James Cotov / MCI ID: 355-4489

TO: Brian Chylik / MCI ID: 681-4566 CC: * Nancy A. Berry / MCI ID: 426-9551 Subject: Internet World's Fair - Amended EO - 12979-00100/ID124608 Message-Id: 92960112154229/0003554489PL1EM