Before the FEDERAL COMMUNICATIONS COMMISSION FCC 96-208 Washington, D. C. 20554 ) In the Matter of ) ) Amendment of Parts 2 and 15 of the ) Commission's Rules to Deregulate ) ET Docket No. 95-19 the Equipment Authorization ) Requirements for Digital Devices ) REPORT AND ORDER Adopted: May 9, 1996 ; Released: May 14, 1996 By the Commission: INTRODUCTION 1. By this action, we are amending Parts 2 and 15 of our rules to streamline the equipment authorization requirements for personal computers and personal computer peripherals. In particular, we are adopting a new "Declaration of Conformity" (DoC) procedure that will permit these devices to be authorized based on a manufacturer's or supplier's declaration that the computer product conforms with all FCC requirements. Under this procedure, a manufacturer or equipment supplier will test a product to ensure compliance with our standards for limiting radio frequency (RF) emissions and will include a statement, attesting to compliance with those standards in the literature furnished with the product. We are also permitting the marketing of personal computers assembled from separate components that have themselves been authorized under a DoC. In such cases, no further testing of the completed assembly will be required. 2. We anticipate that these rule changes will save industry approximately $250 million annually in administrative expenses, while continuing to provide the same level of protection against harmful interference from personal computing devices to radio communication services. In addition, the new rules will eliminate the need for manufacturers to obtain FCC approval before marketing new personal computer products and thus will allow such products to reach the marketplace more quickly. We also believe that our relaxation of the existing regulations, which can be particularly burdensome for small manufacturers, will stimulate competition in the computer industry. Further, these changes will align our equipment authorization requirements for personal computers with those used in other parts of the world. This action is consistent with new authority provided in the Telecommunications Act of 1996 that permits the Commission to authorize the use of private organizations for testing and certifying the compliance of devices or home electronics equipment and systems with FCC regulations. BACKGROUND 3. Parts 2 and 15 of our rules specify regulations and technical standards to control RF emissions from personal computers and computer peripheral devices. These rules ensure that such devices do not cause harmful interference to important communications services such as broadcasting, land mobile services, aeronautical and maritime communications and navigation systems, and amateur radio. The rules specify limits on the radiated emissions and power line conducted emissions from personal computers and computer peripherals. The existing rules further provide that personal computers and computer peripherals must be authorized under our certification procedure before importation and marketing. The certification procedure requires submission of a written application, test report, and fee to the FCC Laboratory, which may also request a sample device for testing. The certification process currently takes about 35 days, but can take longer if additional information must be submitted to complete or correct the application or if a sample is evaluated. 4. In order to meet market demands, several manufacturers, distributors and retailers have been assembling computers using modular computer components such as enclosures, power supplies, and CPU boards. This can result in a wide variety of possible computer configurations, each of which requires testing and authorization. This can be burdensome for manufacturers, especially small assemblers that may build only a few units of any given computer configuration. 5. In the Notice of Proposed Rule Making (Notice) in this proceeding, we proposed to streamline our equipment authorization requirements for personal computers and personal computer peripherals, based on several informal requests from computer manufacturers, distributors and retailers, test laboratories and other interested parties. In particular, we proposed to replace the current certification requirement with a new procedure based on a manufacturer's or supplier's declaration that the computer product conforms with all FCC requirements. We further proposed to require that laboratories testing personal computer equipment for compliance be accredited under the "National Voluntary Laboratory Accreditation Program" (NVLAP) developed by the National Institute of Standards and Technology (NIST). We also proposed to permit the marketing of personal computers manufactured from authorized modular components without additional testing. A total of 57 parties filed comments, and 13 parties filed replies to comments in response to this Notice. A list of commenters is attached as Appendix B. 6. The Telecommunications Act of 1996 (1996 Act), enacted on February 8, 1996, provides the Commission new authority to eliminate unnecessary regulations and functions. In particular, Section 403(f) of the 1996 Act amends Section 302 of the Communications Act of 1934 to allow the Commission to: "1) authorize the use of private organizations for testing and certifying the compliance of devices or home electronic equipment and systems with regulations promulgated under this section; 2) accept as prima facie evidence of such compliance the certification by any such organization; and 3) establish such qualifications and standards as it deems appropriate for such private organizations, testing, and certification." DISCUSSION A. Equipment Authorization Requirements Declaration of Conformity 7. In the Notice, we proposed to relax the equipment authorization requirements for personal computers and personal computer peripheral devices from FCC certification to a new self-authorization process based on a manufacturer's or supplier's declaration of compliance. Under this proposed new equipment authorization procedure, a manufacturer or equipment supplier would test a product to ensure compliance with our standards for limiting RF emissions and would include a statement of compliance with those standards in the literature furnished with the equipment. We proposed that this statement, to be entitled a "Declaration of Conformity," include the following information: 1) identification of the specific product covered by the declaration (e.g., by trade name and model number); 2) a statement that the product complies with Part 15 of the FCC Rules; 3) identification of the compliance test report by date and number; and 4) identification by name, address and telephone number of the manufacturer, importer or other party located within the United States that is responsible for ensuring compliance. Marketing could begin immediately after testing confirms that the product complies with the standards and the DoC is completed. We proposed that the party issuing the DoC would be the party responsible for ensuring compliance with all applicable FCC requirements and that this declaration must be executed before the subject equipment may be imported or marketed. We further proposed that the responsible party furnish the DoC and test report to the Commission within 14 days if requested. 8. We also invited comment on alternative approaches for deregulating the equipment authorization requirements for personal computers and peripherals. We observed that one alternative would be to retain the existing certification requirement, but to permit marketing to begin as soon as the application is filed. We also noted that another option would be to relax the equipment authorization from certification to notification or verification. We further noted that the proposed new process is very similar to the verification procedure. The two principal differences between verification and our proposed self-approval process are that, under the new procedure: 1) manufacturers must include a copy of the Declaration of Conformity with the information furnished to the user; and, 2) testing laboratories must be accredited under NIST's NVLAP program. 9. The great majority of the commenting parties support our efforts to relax the equipment authorization process for personal computing equipment in some manner. Most parties support our proposal for a new procedure based on a manufacturer's or equipment supplier's declaration of conformity. These parties state that the new process will benefit both the computer industry and consumers by reducing costs and allowing new products and technologies to reach the market more quickly. Several parties also submit that lower prices for equipment will make it possible for more consumers to afford and enjoy the benefits of personal computers. For example, Apple and AT&T state that the new process would stimulate competition in the industry by reducing the amount of time it takes manufacturers to get products into the marketplace. AT&T also notes that the DoC would provide consumers with additional information, including the name, address and telephone number of the party responsible for ensuring that the device complies with FCC regulations. The Information Technology Industry Council (ITI) believes that our proposal is a reasonable balance of regulatory and marketplace interests. It states that this proposal will benefit consumers by lowering equipment development costs and making technology available sooner. ITI further states that interference will not increase as a result of the new procedure, since it does not eliminate the requirement for pre-marketing testing. Motorola believes that the proposed process will continue to ensure a high standard of compliance while minimizing regulatory burdens. HP believes the DoC approach is superior to other options, such as our verification procedure, because it would aid efforts to harmonize our equipment authorization requirements with those of other nations. 10. Several parties recommend that we modify the existing certification process for personal computing equipment to permit marketing of devices upon completion of testing or upon submission of an application to the FCC. Vtech Computers (Vtech), for example, recommends streamlining the existing process to permit marketing upon completion of testing. The Association of Federal Communications Consulting Engineers (AFCCE) and Carl T. Jones suggest that we maintain the existing certification process, but allow manufacturers to market products upon submission of an application to the FCC. PCTEST Engineering Laboratory (PCTEST) similarly recommends that equipment authorization be granted as soon as the application is logged in by an FCC applications examiner. It also suggests that we permit electronic filing of applications through the Internet to speed the authorization of personal computers. 11. Other parties suggest that we apply either our notification or verification procedures to personal computers. Washington Laboratories recommends using the notification process. Canon, Compaq Computer Corporation (Compaq), Sony, Texas Instruments (TI) and Unisys recommend that personal computers be subject to the verification process. EIA/CEG, while supporting the use of a DoC for computers manufactured from modular components, recommends that fully assembled computers be subject to verification. 12. A number of commenting parties, including the American Radio Relay League (ARRL), the Association for Maximum Service Television (MSTV), Capital Cities/ABC, GMC Laboratories (GMC) and others, express concern that deregulating the equipment authorization procedures for personal computing equipment could lead to decreased equipment compliance and increased interference to radio communications services. ARRL argues that the proposed changes would make it easier for manufacturers of non- compliant equipment to market such devices and would also make it more difficult for the Commission to enforce compliance. Capital Cities/ABC and others argue that increased enforcement efforts would be needed if such an approach is adopted. Capital Cities/ABC submits that the current equipment authorization program for personal computers is the reason that the FCC does not receive significant complaints of interference from such equipment. Capital Cities/ABC states that the Commission should not lessen the procedures for preventing excessive RF emissions unless it has the resources, personnel and procedures for monitoring and enforcing the rules. MSTV contends that permitting self-approval by parties that have a financial interest in the outcome of testing will result in decreased compliance. These parties argue that we should not relax the current certification requirement for personal computers and peripherals. 13. With regard to the information to be contained in the DoC, AT&T, Compaq, EIA/CEG, IBM, the Information Technology Association of Canada (ITAC), Spirit, TI, and Unisys believe that including the test report number and date in the DoC is burdensome and unnecessary. EIA/CEG argues that the DoC should only contain a notice that the equipment complies with Part 15 and the identification of the party responsible for ensuring compliance. IBM and ITAC point out that any modifications to the equipment would require retesting and thereby necessitate costly revisions and reprinting of the product user manual that would provide little benefit to consumers. ITAC indicates that only the name and address of the responsible party should be required in the DoC. AT&T also suggests that the responsible party listed in the DoC should include the name, address and telephone number of the manufacturer or importer, if the manufacturer is not located in the United States. TI suggests that a reference code be used to identify the responsible party. Elite Electronic Engineering Company (Elite) recommends that the DoC include the name of the testing laboratory only if the tests are conducted by an independent laboratory. 14. Several parties, including Apple, AT&T, Compaq, ITI, Bruce Reynolds, Sony, Unisys and Xerox, recommend that manufacturers have the option of providing instructions on how to obtain a copy of the DoC in the user manual, rather than including a copy of the DoC with each product. Compaq indicates that the inclusion of a flyer insert adds an additional step in production that could cause added cost and delays due to errors during packaging. Sony believes that it is unnecessary to include a copy of the DoC with each product and instead supports an expanded labelling requirement that provides information about the appropriate contact person. 15. Several parties discussed the proposed 14 day period for submission of the DoC and test report upon Commission request. Computing Technology Industry Association (CompTIA), Gateway, and IBM believe a 14 day period is sufficient for providing a copy of the DoC to the FCC. IBM requests clarification that the time frame begins at the time of receipt of the FCC request. ITAC requests clarifications of the intention of the 14 day period and recommends adoption of a longer period. ITI and PCTEST argue that 30 days is needed for submission of the test report to the Commission. PCTEST also recommends that the test report and test sample be required to be held for three years. 16. Several parties, including Apple, the Coalition of Concerned Independent Testing Laboratories (CCITL), Compliance Engineering Services (CES), Dell Computer Corporation (Dell), Electromagnetic Engineering Services, Inc. (EESI), Mark Lapchak, and Bruce Reynolds, recommend that some form of FCC filing should be required as part of the DoC process. Apple believes that manufacturers and suppliers should be required to submit a copy of the DoC to the Commission when a product is offered for sale. CCITL suggests that a minimum FCC filing requirement be adopted and that the information provided on filings under this requirement should be listed on the FCC Laboratory's "Public Access Link" system. CCITL proposes that the filing requirement include an identifying number, brief description of the equipment, photographs, DoC statement, and the identity of the test lab. Dell recommends requiring that a copy of the DoC always be submitted to the FCC, rather than only upon request. CES and EESI recommend that some form of FCC filing be maintained and support continued use of FCC ID numbers. 17. Decision. The record in this proceeding provides significant support for our efforts to relax the equipment approval requirements for personal computing devices. We continue to believe that our proposal to establish a new procedure based on a manufacturer's or supplier's declaration of conformity is the most appropriate method for authorizing personal computers and peripherals. 18. We believe that the new DoC process will provide a number of important benefits for manufacturers and suppliers of personal computing equipment and that these benefits would accrue to businesses and consumers as well. Initially, we observe that this new equipment approval process will permit manufacturers to introduce new equipment into the market more rapidly and to avoid a substantial portion of the costs involved in the current certification process. We also believe that reducing the time-to-market of computer products will allow manufacturers and suppliers to compete more effectively in the market for these products. Further, the new process will protect manufacturers' and importers' business interests by eliminating the premature disclosure of new products that occurs in the filing of applications for certification. These improvements for manufacturers and suppliers can be expected to benefit consumers in the form of lower prices, additional product features and improved product quality. 19. We do not agree with comments expressing concern that implementing the DoC procedure will result in increased non-compliance of personal computers and computer peripheral devices. These devices must still be tested to ensure compliance with our standards. As long as the measurement procedures are properly followed and testing is performed by a competent laboratory, there appears to be no valid reason why compliance under the DoC procedure should be any different than under our existing certification procedure. We also do not agree that it is necessary to mandate the automatic filing of information with the Commission. The DoC will provide a clear indication that the product complies with our requirements and will provide a mechanism for identifying responsible parties should questions arise regarding compliance. We believe that an additional requirement for filing of information with the FCC would not provide any added assurance of compliance and would create an unnecessary administrative burden. In summary, we find that the new DoC procedure will substantially reduce the burden of equipment authorization on manufacturers and importers of personal computer equipment without significantly raising the risk that such equipment will cause harmful interference to communications users. 20. We also observe that this new equipment authorization procedure is similar to product approval programs for digital devices employed in other parts of the world. In Europe, for example, manufacturers are permitted to self-declare compliance with radio noise standards for personal computer equipment. There is growing interest in the international harmonization of standards, test methods and product approval procedures to better facilitate trade. We have, in fact, taken actions in the past to harmonize the standards and measurement procedures for personal computer equipment with those accepted internationally. We believe our DoC plan may advance the acceptance of U.S. product approvals for personal computers and their associated peripherals in other countries. This could potentially provide U.S. manufacturers easier access to foreign markets, thereby creating jobs and enhancing U.S. economic growth. 21. We do not agree with the comments suggesting that it would be more appropriate to streamline our existing certification procedure, or to use our notification or verification procedures. Streamlining the certification process or using the notification procedure would place a larger burden on both industry and FCC staff than the DoC approach, without a significantly increased benefit to the public. Furthermore, there are potential problems with these approaches. For example, if we were to permit products under certification or notification to be marketed upon submission of an application to the Commission, paperwork and other administrative errors in that submission could result in a manufacturer having to cease all marketing while problems with the application were corrected. This could result in a costly burden to the manufacturer. We also do not believe that our verification process would provide sufficient information and safeguards to ensure compliance with regard to computer technology, which is continuing to evolve rapidly. Further, verification would appear inconsistent with international approaches for approval of personal computers and peripherals. 22. We agree with the comments that the requirement to include the name of the test laboratory and the date on which compliance testing took place would pose an unnecessary burden. Computers and peripheral devices sometimes go through several modifications in short periods of time, each of which requires retesting. Requiring the test laboratory information to be updated each time these tests are made could result in an administrative burden. While this information will have to be readily available to the FCC, upon request, it generally serves no purpose for the consumer and therefore is not needed on the DoC. We believe that it is important to include a copy of the DoC with the product either as a separate insert or in the user's manual, to verify compliance of a product and provide a readily accessible contact person for inquiries from consumers and the FCC. We do not believe that providing the minimal information requested in a DoC will pose an undue burden. Accordingly, we will require that the DoC statement be included with the equipment and contain the following information: 1) identification of the specific product covered by the declaration, such as by trade name and model number; 2) a statement that the product complies with Part 15 of the FCC Rules, similar to the statement currently required under Section 15.19(a)(3) of the regulations; and 3) the identification by name, address and telephone number of the manufacturer, importer or other party located within the United States that is responsible for ensuring that the equipment complies with the standards. The DoC statement may be included as a separate document or may be included in the user's manual supplied with the product. 23. The party responsible for ensuring compliance will be required to submit, upon request, documentation verifying compliance, including test reports, to the Commission within 14 days of such a request. With the availability of express and overnight delivery services, 14 days is ample time to submit documentation that is required to already be readily available. We clarify that this 14 day period begins upon the delivery of the request to the responsible party. Finally, we do not agree with the request that the test report and test sample should be held for three years. We believe that it is important to retain this information for a sufficient length of time to verify compliance with our rules in enforcement matters. We note that under the certification process, where the Commission has reviewed the application and data and granted an authorization, we require the retention of records for one year after the manufacturing of a product is discontinued. However, under the notification and verification processes, where the Commission has not reviewed the application and data, we require the retention of records for two years after manufacturing is discontinued. Accordingly, since the new DoC process will not require prior review by the Commission and since we want to maintain consistency with our other equipment authorization processes, we will require the manufacturer to retain a record of all documentation for a period of two years after manufacturing is discontinued. Labelling Requirement 24. Under our current rules, personal computers and peripherals must be labelled with an "FCC ID" and a general statement of compliance with the standards. In the Notice, we proposed to require that personal computers and peripherals display a small logo to indicate compliance with FCC Rules. This logo would be similar to the "UL" logo used by products that comply with standards developed by the Underwriters' Laboratories or the "CE" logo that indicates compliance with European standards, and would replace the existing FCC ID label requirements. Comments were invited on the specific format for such compliance labelling. We also invited comments as to whether this labelling is necessary and whether the benefits of this requirement warrant the costs. No changes were proposed to the existing requirement to provide information in the user manual regarding steps to be taken in the event the equipment causes interference. 25. The commenting parties support improvements to the existing labelling requirements for personal computers and peripherals. Most parties recommend that we adopt a simple, easily recognizable logo. Apple, Cannon, IBM, ITAC, and Bruce Reynolds support the use of a small compliance logo. They also recommend coordination with Canada and Mexico to develop a NAFTA logo as long as it would not cause a delay in the adoption of the proposal. HP and TIA recommend use of a logo that is suitable for multinational use and support a simple logo that references the FCC or CISPR class. Gateway agrees that a logo identification is necessary to provide reassurance to consumers that a product meets appropriate standards. However, it submits that a North American logo is unnecessary, as Mexico and Canada currently accept the FCC ID for radiated and conducted emission compliance. CKC and Compaq suggest that we recognize the CE mark as equivalent label to the FCC label. 26. CompTIA supports the use of a simple label similar to the "Intel Inside" logo. IBM and TI urge that the label include a "A" or "B" to designate the emission class of the device. ITI and ITAC believe that a pictorial logo is appropriate for devices assembled and tested by manufacturers but urges adoption of a special label for computers assembled with modular components. HP recommends that systems assembled from components should not indicate that the computer complies with Part 15. It states that only systems that are tested as such should claim conformity on their DoC. Silicon Graphics believes simple text labelling is adequate and that an FCC logo is unnecessary. However, it states that extensive labelling notifying the user of potential interference should be used for computers composed of modular components. 27. EESI supports the use of a compliance logo and a text-based product label similar to the current label. Intel believes that the current label is adequate, when coupled with the warning text required in the manual. ICC proposes a modified version of the current label that would include a "DoC ID" number composed of codes for the grantee, NVLAP lab and the test report number. Sony recommends a permanent label that states compliance and includes an address or phone number for the responsible party to contact in case of any interference or to obtain a copy of the test report. On the other hand, M. A. Plante recommends that the logo not contain variable information that is unique to the product. Xerox opposes maintaining the current warning statement on the label and instead believes that any warnings should be placed in the user manual. Finally, Gateway, M. A. Plante and Tokin agree that it will still be necessary to include an informational statement in the user's manual regarding steps to be taken in the event of interference. 28. Decision. As proposed, we are replacing the existing FCC ID label on personal computing equipment with a new, simplified label that includes a compliance logo. We believe that the new label and FCC logo will increase public awareness of our technical standards and testing requirements for personal computers and will promote demand for properly approved devices. Further, we are specifying separate labels for products that are assembled and tested by manufacturers and those that are assembled from modular components. This will provide information for FCC enforcement purposes and will also inform consumers of the differences in the manner in these devices comply with the rules. Consistent with our existing rules, we are also requiring that the new labels for computing devices uniquely identify the product with a trade name and type or model number. This will ensure that equipment marketed under more than one brand name can be properly identified in a request for documentation verifying compliance. 29. In choosing a logo and label format, we considered the following factors: 1) the logo should be easily recognizable; 2) the logo and label should convey information about its purpose; and 3) the label information and message should be simple and easily understandable. Accordingly, we have designed the following two labels: 30. We recognize the advantages of having a uniform labelling requirement and logo that could be accepted throughout North America or the world. We intend to pursue the development of a common international compliance label for personal computing devices and encourage industry support of efforts in this regard. When such a label and/or logo is developed, we will revisit our labeling requirements for personal computing equipment. As a final matter, we are requiring that all warning statements regarding interference potential be placed in the user manual, rather than on the label as is currently required. The user manual contains general operating instruction on the use of a device and we believe that placing the warning statements in the user manual would better server the consumer. We are also maintaining our requirement that an informational statement be included in the user's manual regarding actions the user can take to resolve any interference that may occur from use of the device. Accreditation of Test Laboratories 31. In the Notice, we indicated that it was important under a self-authorization program to ensure that laboratories can adequately perform the compliance testing. Accordingly, as noted above, we proposed that laboratories testing personal computers and personal computer peripheral devices be accredited under the NIST's NVLAP program. We observed that laboratory accreditation is generally required, either implicitly or explicitly, under most foreign product approval procedures. We also requested comments on whether to permit alternative methods of accrediting laboratories, such as that offered by the American Association for Laboratory Accreditation (A2LA). We further asked for comment on whether the laboratory accreditation requirement should apply to manufacturer's laboratories. We proposed a transition period of two years to permit laboratories to obtain NVLAP accreditation. Within that two-year period, laboratories that had not been accredited would be allowed to continue to obtain authorizations of personal computers and peripheral devices under the current certification procedure. 32. Several parties, such as CCL, ICC, M. A. Plante, Motorola and Norand, support the proposed requirement for NVLAP accreditation of laboratories that test personal computer equipment. Motorola states that accreditation through NVLAP would offer a number of advantages for the U.S. industry and would support U.S. efforts for international harmonization of equipment approval. CCL similarly observes that laboratory accreditation is being imposed in other parts of the world such as Australia, South Korea, Canada, Mexico and Europe. In addition, a number of parties, including A2LA, C&C Laboratory, Cannon, Carl T. Jones, CES, CCITL, CKC, CompTIA, Diversified, EESI, Gateway, IBM, Intellistor and Bruce Reynolds support accreditation of testing laboratories, but request that alternatives to NVLAP accreditation be permitted. These parties observe that NVLAP accreditation is costly and that currently there are only a limited number of NVLAP approved labs. They recommend that private sector accreditation be permitted. A2LA estimates that it could provide accreditation at about two-thirds the cost of NVLAP accreditation. Carl T. Jones believes that some accreditation program may be necessary, but does not agree that NVLAP is the appropriate program. EESI supports lab accreditation and recommends that the NIST National Voluntary Conformity Assessment System Evaluation (NVCASE) program be used to accredit a minimum of five competing Registrars for EMC test lab accreditation. Intellistor also agrees that some method of laboratory accreditation is needed, but is concerned about the cost of NVLAP accreditation. 33. Apple, Certitech, Dell, Elite, HP, ITI, ITAC and Retlif, support mandatory accreditation for independent labs, but not for manufacturers' labs. Apple, Certitech, Dell, HP and ITI recommend that the current FCC site registration program be continued for manufacturers' labs. Apple states that we should permit manufacturers' test facilities to choose between NVLAP approval or FCC site listing. Apple also recommends that we model our site registration program on ISO 9000. Certitech recommends that the FCC site registration program be improved to include periodic FCC inspections of labs and indicates that these inspections could be funded by a registration fee. On the other hand, CCITL, CES, EESI, PCTEST and Timco believe that accreditation should apply equally to all testing labs, including manufacturers' labs. For example, Timco states that accreditation can only be fairly implemented if it is applied to all test facilities. 34. Other parties, including AT&T, Burle, Certitech, Compaq, Dell, EIA/CEG, GMC, HP, IBM, ITI, Mark Lapachak, MicroENERGY, NEC, Michael Nicolay, SGI, Sony, Spirit, Sun, TI, Unisys and Xerox, oppose any requirement for mandatory accreditation of testing labs. These parties argue that the added cost and burden of accreditation are not warranted. For example, AT&T argues that currently approved personal computers are not causing harmful interference even though the testing is conducted by non-accredited labs. Certitech states that NVLAP accreditation does nothing to support the goal of streamlining the certification and marketing of computers. Compaq states that the current system works and that we should not adopt a lab accreditation program. ITI believes that mandatory accreditation would not promote international harmonization and would be viewed as a trade barrier by off-shore manufacturers. Unisys states that NVLAP accreditation does not appear to be justifiable in the context of deregulation. Xerox believes that accreditation should only be used as a means to achieve international reciprocity. It notes, however, that Japan currently accepts FCC site registration without requiring further testing. 35. AT&T, CES, Hong Kong, Intel and Tokin submitted comments regarding the accreditation of foreign labs. AT&T and Intel state that mandatory accreditation could result in barriers for foreign manufacturers. CES states that foreign labs should only be permitted to participate in accreditation if laboratories in the United States are granted authority to participate in equipment authorization in the European Union countries and others. Hong Kong requests that we consider recognizing labs that have been accredited under the Hong Kong Laboratory Accreditation Scheme (HOKLAS) and adds that HOKLAS already has an agreement with A2LA. Tokin recommends that we accept laboratory accreditations from foreign countries based on agreements between NIST and other countries. 36. A2LA, Gateway, ICC and Motorola support the proposed two-year transition period, during which parties would have the option of obtaining certification or using the DoC process while labs are obtaining NVLAP accreditation. These parties state that a two-year period seems adequate. Other parties including Certitech, CCITL, EIA/CEG, and IBM recommend a four-year transition period, while Washington Laboratories recommends three years. These parties argue that a longer time period is needed because of the large number of labs that will need accreditation. CCITL recommends four years to allow accreditors other than NVLAP to form programs. It states that accreditation should not be a requirement for a lab to perform DoC testing until the transition period is over. Compaq argues that the requirement to use certification while waiting for NVLAP accreditation would provide an unfair advantage to laboratories that are already NVLAP accredited. 37. Decision. We continue to believe some form of laboratory accreditation is important and necessary for ensuring the proper testing of digital devices for compliance with our rules. Although our existing equipment certification procedure does not require that test laboratories be accredited, the procedure does give our staff the opportunity to review the report on compliance testing before a product can be marketed. Under the new self- authorization DoC procedure, we will be relying solely on the test labs to ensure that the testing is performed correctly. The requirement for accreditation of test laboratories will provide greater confidence that the testing laboratory has the capability to do proper testing and will provide a means for excluding laboratories that are not properly qualified. In addition, a requirement for accreditation will more closely align our computer authorization procedures with those of other countries. As indicated by Motorola and others, accreditation may not always be explicitly required by other countries, but their procedures often effectively impose an accreditation requirement. We therefore will require that laboratories testing personal computers and peripherals under our new DoC procedure be accredited by an appropriate recognized entity. 38. We continue to believe that accreditation under NIST's NVLAP program will ensure that personal computers are properly tested for compliance with our rules. At the same time, we note that a number of the commenting parties expressed concern regarding the use of NVLAP as the exclusive means for accreditation and that alternative means of accreditation should also be permitted. We agree that allowing additional parties to accredit test laboratories will reduce the cost and time needed to obtain accreditation and intend to permit laboratory accreditations by other parties. For example, we are familiar with the A2LA's accreditation program and believe that it too would provide appropriate assurance of the competence of test laboratories that test personal computing equipment. Accordingly, we will accept laboratory accreditation by the NIST NVLAP program, the A2LA accreditation program, and by other organizations approved by the FCC for purposes of testing personal computer equipment under our DoC procedure. In order to ensure the integrity of the laboratory accreditation program, we are instructing our staff to periodically review the accreditation process and maintain close coordination with NIST, A2LA and any others that may be performing accreditations. We are also delegating to the Chief of the Office of Engineering and Technology the authority to recognize additional accrediting organizations and to make determinations regarding the continued acceptability of individual accrediting organizations and accredited laboratories. 39. We are not persuaded that laboratories affiliated with manufacturers should be excluded from accreditation. No persuasive evidence has been presented in the record of this proceeding to indicate that manufacturers' laboratories are more likely to perform compliance testing of personal computers in a manner that is more acceptable than independent laboratories. We also agree with those commenters who argue that excluding manufacturers' test labs from required accreditation would place them at an unfair advantage over parties, such as small businesses, that must employ independent test laboratories where accreditation would be required. Accordingly, we will require that any laboratory that tests digital devices for compliance under the DoC process must be accredited through an approved accreditation program. 40. We believe that our laboratory accreditation requirement will support efforts towards international harmonization. One of the barriers to foreign acceptance of United States product approvals has been the lack of a process for assuring the quality of laboratory testing in the U.S. We believe our laboratory accreditation requirement will provide the assurance of testing quality needed by foreign administrations to accept U.S. test results. This would benefit our manufacturing industry in international trade by eliminating the need for additional testing to market U.S. products in foreign countries. In the interests of promoting fair competitive trade, we intend to work closely with administrations of other countries to develop mutual recognition agreements regarding acceptance of the accreditations of both U.S. and foreign laboratories. At the same time, we agree with CES that it would be unfair to accept the accreditation of labs from foreign countries that either do not accept U.S. accreditations or that impose additional barriers upon U.S. companies. Accordingly, for purposes of our DoC procedure, we will accept accreditation of foreign laboratories from countries with whom the United States has a mutual recognition agreement to accept the accreditation of U.S. laboratories. Foreign manufacturers using non-accredited laboratories may continue to seek equipment approval for personal computing devices under our certification procedure. 41. We now believe that we should continue to allow certification of personal computing equipment on an indefinite basis. This will allow manufacturers and importers of personal computing equipment to use either the new DoC procedure or the certification procedure for authorization of personal computing equipment, whichever best meets their individual needs and circumstances. Consistent with this approach, we find that no special transition period is needed with regard to the implementation of the DoC procedure. While we recognize that currently accredited laboratories may have some initial advantage in that they will be able to perform testing under the DoC procedure sooner than others, this advantage should be mitigated by our decision to permit additional parties to accredit laboratories. Further, we find no compelling reason to penalize manufacturers and importers desiring to take advantage of our new self-authorization process by delaying the initiation of that procedure until all laboratories can obtain accreditation. B. Authorization of Modular Personal Computers 42. In the Notice, we proposed to require that all CPU boards, power supplies, and enclosures designed for use in personal computers and marketed separately to the public be authorized to demonstrate compliance with the technical standards contained in Part 15 of our rules. We also proposed to allow any party to assemble and self-approve a personal computer using authorized components or to interchange these components in an existing personal computer system without the need to retest the resulting system, provided the assembly instructions provided with the components are followed. We indicated that the assembler would be required to issue a new DoC indicating the basis on which compliance was ensured, e.g., only authorized components were used in the assembly or authorized components were installed in an authorized system. We further proposed to require that the DoC identify each component used in the computer, include a statement that the computer complies with Part 15 of the FCC Rules, identify the compliance reports for each product used in the computer by date and number, and identify by name, address and telephone number the assembler responsible for ensuring that the resulting system complies with the standards. 43. In the Notice, we proposed to define a CPU board as a circuit board that contains a microprocessor, or frequency determining circuitry for the microprocessor, the primary function of which is to execute user-provided programming, but not including: 1) a circuit board that contains only a microprocessor intended to operate under the primary control or instruction of a microprocessor external to such a circuit board; or 2) a circuit board that is a dedicated controller for a storage or input/output device. We proposed to require that the CPU board be tested twice to help ensure it would be likely to comply with our emissions requirements in different modular computer configurations. In the first test, the CPU board would be tested without an enclosure and connected to a power supply with the oscillator circuit for the microprocessor operating with the output coupled to the microprocessor circuit, as would occur under normal operation. No peripheral devices would be connected during this first test, and only radiated emissions would be measured. Further, under this first test, we proposed to permit the radiated emissions to exceed the limits specified in our rules by a specified amount, e.g., 6 dB. The second test of the CPU board would take place with the CPU board installed in a representative enclosure, with a representative power supply, and configured in the manner currently specified under our rules. This second test would demonstrate compliance with the appropriate standards for both radiated and conducted emissions. We requested alternative suggestions to this proposal along with comments as to how to deal with the fact that a CPU board may be capable of accepting microprocessors from multiple manufacturers. 44. We proposed to permit power supplies to be authorized based on a single test with the power supply installed in a typical configuration. We proposed that enclosures for personal computers, be shown to provide 6 dB of shielding effectiveness across the spectrum from 30 MHz to 1000 MHz. We added that the DoC for the enclosure would be required to specify the particular types of CPU boards for which it is authorized (e.g., for use with "486DX2" CPU boards). We also proposed to require that any special steps necessary to ensure compliance be explained in the installation instructions. Finally, we proposed to prohibit authorization of CPU boards or internal power supplies that require complex electrical changes to the host system, such as soldering parts or altering circuitry. 45. The responses to the proposals for self- authorization of personal computers using modular components varied greatly. A number of commenting parties, including Apple, CompTIA, HP, ICC, ITAC, ITI, Intellistor, Mark Lapchak, Motorola, Bruce Reynolds, Spirit, Unisys, and Xerox support permitting the authorization of modular computers that are assembled from approved components. HP states that modular component authorization approach will increase the likelihood that computers built by system integrators will comply with the Commission's technical standards. ITAC states that permitting the self-authorization of modular computers will level the field between manufacturers who have been complying with current testing rules and system integrators who have not been performing compliance testing. ITI believes that imposing a DoC program for components will improve the likelihood of industry compliance, especially in cases where regulations have previously been ignored. CompTIA supports the proposal, but argues that the proposed requirement for the assembler to issue a new DoC would be burdensome. ICC recommends that the assembler not be held responsible for system compliance if all the components used are DoC approved. Intellistor believes that technical standards should be expanded to also include devices, such as hard drives, video boards and other components, to help ensure the assembly of a compliant system. Unisys also recommends requiring testing of other components such as accelerator cards, microprocessor upgrades and interconnecting cables. Xerox recommends that the rules on modular assemblies should encompass all modular components and devices to avoid confusion over whether products such as printers or other peripherals are covered under the new procedures. It also recommends that manufacturers be required to provide specific instructions regarding the use of any special cabling or any restrictions on uses in the documentation included with the device. 46. Apple believes that computers assembled from modular devices should be subject to tighter emissions limits than the present FCC Class B limits and some form of special labelling. It suggests that we subject power supplies and CPU boards to emissions limits that are 6 dB below the current limits for personal computers and that we require that component devices be tested in a minimum configuration. 47. A number of other parties, including AFCCE, AST, AT&T, Capital Cities/ABC, Carl T. Jones, CCITL, Dell, Gateway, MicroENERGY, MSTV, Michael Nicolay, SGI, Sony and TI believe that the modular computer proposal presents a risk of increased interference, and are opposed to any changes that would eliminate testing of the final assembled system. AFCCE, for example, states that the proposal fails to recognize that the final configuration of a system is an important factor in determining compliance. AST states that there is no guarantee that a system assembled from approved subassemblies or components will comply with the rules. AST is further concerned that double testing of a single product may be required, i.e., both the component and the final assembled system, and that this would increase costs. AT&T believes that assembly of new computers from authorized components should not be allowed until further data is available. Capital Cities/ABC states that testing components is not an adequate substitute for testing finished products. Compaq believes that the modular approach will reduce rather than enhance compliance and make enforcement virtually impossible. Dell also argues that authorization of modular computers would provide system assemblers and unfair competitive advantage over manufacturers. SGI states that modular computer compliance by testing components is technically incorrect and unsound. SGI recommends, at a minimum that any emission limit for components be set at minus 6 dB below the present Class B limits. 48. Gateway, Intellistor and ITAC comment on our proposed two-step testing of CPU boards. Intellistor states that the proposed two-step testing plan for CPU boards has merit but recommends that the procedures for such testing be developed through a joint FCC and ANSI subcommittee. Gateway and ITAC oppose the two-step testing plan. Gateway states that it will be difficult to ensure that a board that is permitted to exceed the limit during the first test will later comply when installed in a system. ITAC believes assemblies should be tested in a representative configuration under the current procedures. 49. CCITL, Dell, Gateway, Intellistor, Motorola and Sony support some type of separate authorization plan for power supplies. Dell, while opposing authorization of other components, states that modular approval does seem justifiable for power supplies. Similarly, Gateway submits that the power supply primarily affects the ability of a computer to comply with the conducted limits and therefore can be authorized separately. CCITL states that power supplies should be subjected to full and half resistive loads on power supplies to demonstrate compliance with the conducted emissions limits. Intellistor suggests that power supplies be pre-scanned with a minimum and maximum load and then tested with a typical CPU to identify the broadband characteristics of the power supply. Motorola also agrees with the proposal for separately authorizing power supplies. Sony recommends permitting power supplies to be tested with a non-inductive dummy load at the maximum rated output power as an alternative to testing in a typical configuration. However, AT&T argues that a power supply that is compliant when tested in one typical configuration may not comply in other configurations. 50. Several parties, including Apple, AT&T, Gateway, Intellistor and MicroENERGY oppose the establishment of shielding standards for computer enclosures. Apple believes that enclosures should not be authorized as stand-alone devices. AT&T states that there is no practical way to determine the effectiveness of an enclosure in shielding emissions from within due to the existence of seams, slots and other factors. Gateway states that the proposal to specify the types of CPU boards for an enclosure may not be a proper solution because certain boards can use different CPUs. Gateway is concerned that a shielding requirement would necessitate that manufactures to carry inventories of different enclosures to match different combinations of motherboards and CPUs. Intellistor recommends that testing enclosures be further studied. MicroENERGY believes that it is risky to expect that a cabinet will provide the same amount of shielding for different motherboards. On the other hand, CCITL recommends that computer chassis should be subject to shielding effectiveness. Unisys expresses concern that demonstrating shielding effectiveness is very difficult. 51. Decision. As observed in the Notice, an increasing number of personal computers are now being custom assembled from modular components, including CPU boards, power supplies and enclosures. This modular component approach provides manufacturers and system integrators flexibility to produce a wide variety of equipment models to meet consumer needs. Under our current rules, each combination of CPU, power supply and enclosure must be separately tested for compliance. We continue to believe that there is need for a simpler means of authorizing computers assembled from modular components. At the same time, we also need to ensure that such a simpler approach does not permit such modular computers to pose a greater risk of interference. We find that a self-authorization DoC approach that permits the assembly of computers from authorized modular components with a requirement for some additional testing would provide both flexibility for manufacturers and system integrators and adequate assurance that such modular computers will comply with our technical standards. Based on the record in this proceeding, however, we are modifying our original proposal to tighten the emission limits for CPU boards tested without an enclosure to provide added assurance that modular computers will comply with our technical standards. Due to the difficulties associated with determining the shielding effectiveness of enclosures, we are not adopting our proposal to separately authorize enclosures. Accordingly, we are adopting the approach described below for authorizing modular computers. This approach, which is similar to that proposed in the Notice, will allow any party to integrate personal computer systems using authorized components without the need to retest the resulting system. Manufacturers will also continue to have the options of using the certification procedure or the new DoC procedure for personal computer equipment. As part of this plan, we are requiring that any special steps needed to ensure compliance of a component must be explained in the installation instructions. 52. Since the design of the CPU board is a critical factor in determining whether the completed computer system will comply with the standards, we believe it is essential that computers constructed from modular components employ CPU boards that are, themselves, designed to ensure compliance with our technical standards. To ensure that such CPU boards will comply with these standards, we are requiring that CPU boards be authorized under either the DoC or certification procedures and be tested for compliance in the following manner. Testing for radiated emissions shall be performed with the CPU board installed in a typical enclosure but with the enclosure's cover removed so that the internal circuitry is exposed at the top and on at least two sides. Additional components, including a power supply, peripheral devices, and subassemblies, shall be added, as needed, to result in a complete personal computer system. If the oscillator and the microprocessor circuits are contained on separate circuit boards, both boards, typical of the combination that would normally be employed, must be used in the test. Testing shall be in accordance with the procedures specified in Section 15.31 of our rules. Under these test conditions, the system under test shall not exceed the radiated emission limits specified in Section 15.109 by more than 3 dB. If the initial test demonstrates that the system is within 3 dB of the limits, a second test shall be performed using the same configuration described above but with the cover installed on the enclosure. Testing shall be in accordance with the procedures specified in Section 15.31 of our rules. Under these test conditions, the system under test shall not exceed the radiated emission limits specified in Section 15.109 of our rules. If, however, the initial test performed with the internal circuitry exposed demonstrates compliance with the radiated emission standards in Section 15.109, the second test is not required to be performed. The test demonstrating compliance with the AC power line conducted limits specified in Section 15.107 of our rules shall be performed in accordance with the procedures specified in Section 15.31 using an enclosure, peripherals, power supply and subassemblies that are typical of the type with which the CPU board under test would normally be employed. 53. The design of the power supply used in a personal computer is critical for ensuring compliance with the AC line conducted emissions limits. The amount of load placed on the power supply can significantly alter its emission characteristics. We therefore do not agree that power supplies should be tested as stand-alone products or with only resistive loads that may not be representative of normal loading. Accordingly, we are adopting our original proposal to require that power supplies be tested in a representative personal computer system. We believe that testing power supplies in a representative system will provide a more accurate depiction of emission levels, both conducted and radiated. A power supply that has been tested in this manner and found to comply with the emissions limits may be authorized under either the DoC or certification procedures for use in modular computers. 54. We concur with the commenting parties regarding the difficulties associated with testing enclosures for shielding effectiveness. In particular, we recognize that enclosures for personal computers can affect the emission characteristics of the components contained within the enclosure and that these effects may vary with different components and their placement within the enclosure. We believe, however, that the standards and test procedures we are establishing for CPU boards and power supplies should be sufficient to eliminate the need to specify standards for enclosures. Should we find compliance problems due to ineffective shielding, we may revisit standards for enclosures in a future proceeding. 55. In summary, as proposed in the Notice, we are permitting the assembly, without additional testing, of personal computer systems from separate authorized components. The assembler must follow all of the installation instructions for the separate components in assembling the system. The assembler of the system also must label the system as indicated above and include a separate DoC for the completed system. The DoC must provide a list of all individual components used in assembling the system along with the name, address and telephone number of the company performing the assembly. The assembler of the system will be the party responsible for ensuring that the system complies with the standards. The assembler, upon notification that a specific system combination does not comply with the limits or is causing harmful interference problems, must immediately cease using that combination of components until the problem is corrected and take any additional remedial actions the Commission may deem necessary. Finally, we will not permit the separate authorization of CPU boards or internal power supplies that require complex electrical changes to the host system, such as by soldering parts or altering circuitry. Such equipment may not be used in personal computers assembled from authorized modular component unless the resulting system is tested for compliance with the technical standards. PROCEDURAL MATTERS 56. Final Regulatory Flexibility Analysis. The Final Regulatory Flexibility Analysis, required by the Regulatory Flexibility Act of 1980, 5 U.S.C. Section 608, is contained in Appendix A. ORDERING CLAUSES 57. IT IS ORDERED that Part 15 of the Commission's Rules and Regulations ARE AMENDED as specified in Appendix C, effective 60 days after publication in the Federal Register, upon clearance from the Office of Management and Budget on the information collection requirements, or 60 days from submission of a report to Congress in compliance with the Contract with America Advancement Act of 1996, whichever is the later date. IT IS ALSO ORDERED that the proceeding in GEN Docket No. 90-413 IS TERMINATED. The authority for issuance of this Report and Order is contained in Sections 4(i), 301, 302, 303(e), 303(f), 303(r), 304 and 307 of the Communications Act of 1934, as amended, 47 U.S.C. Sections 154(i), 301, 302, 303(e), 303(f), 303(r), 304 and 307. 58. For further information regarding this Report and Order contact Anthony Serafini, Office of Engineering and Technology, (202) 418-2456. FEDERAL COMMUNICATIONS COMMISSION William F. Caton Acting Secretary APPENDIX A FINAL REGULATORY FLEXIBILITY ANALYSIS Pursuant to 5 U.S.C. Section 603, an Initial Regulatory Flexibility Analysis was incorporated in the Notice of Proposed Rule Making (NPRM) in ET 95-19. Written comments on the proposals in the NPRM, including the Regulatory Flexibility Analysis, were requested. The following Final Regulatory Analysis has been prepared: Need and purpose of this action: This action determines the standards, test procedures, and equipment authorization requirements that will be applied to personal computers in order: 1) to reduce regulatory burdens on computer manufacturers; 2) to remove impediments to flexible system design and construction techniques for computers; and, 3) to reduce the potential for interference to radio services by improving our ability to ensure that personal computers comply with our standards. Summary of the issues raised by the public comments in response to the Initial Regulatory Flexibility Analysis: No commenting parties raised issues specifically in response to the initial regulatory flexibility analysis. Significant alternatives considered: None. APPENDIX B COMMENTING PARTIES Parties Filing Comments: 1. American Association for Laboratory Accreditation (A2LA) 2. The American Radio Relay League (ARRL) 3. Apple Computer, Inc. (Apple) 4. The Association for Maximum Service Television (MSTV) 5. The Association of Federal Communications Consulting Engineers (AFCCE) 6. AST Computers (AST) 7. AT&T 8. Burle Industries, Inc. (Burle) 9. C&C Laboratories (C&C) 10. Canon 11. Carl T. Jones 12. Certitech Corporation (Certitech) 13. CKC Laboratories, Inc. (CKC) 14. Coalition of Concerned Independent Testing Laboratories (CCITL) 15. Communication Certification Laboratory (CCL) 16. Compaq Computer Corporation (Compaq) 17. Compliance Engineering Services, Inc. (CES) 18. Computing Technology Industry Association (CompTIA) 19. Consumer Electronics Group of the Electronic Industries Association (EIA/CEG) 20. Dell Computer Corporation (Dell) 21. Diversified T.E.S.T. Technologies, Inc. (Diversified) 22. Electromagnetic Engineering Services, Inc. (EESI) 23. Elite Electronic Engineering Company (Elite) 24. Gateway 2000, Inc. (Gateway) 25. GMC Laboratories (GMC) 26. Hewlett-Packard Company (HP) 27. Hong Kong Economic and Trade Office 28. International Business Machines Corporation (IBM) 29. The Information Technology Industry Council (ITI) 30. The Information Technology Association of Canada (ITAC) 31. Intel Corporation (Intel) 32. Intellistor O.A.T.S. (Intellistor) 33. The International Compliance Corporation (ICC) 34. Larry Lambert 35. Mark Lapchak and Associates 36. MicroENERGY, Inc. (MicroENERGY) 37. Motorola 38. NEC Technology (NEC) 39. Michael Nicolay 40. Norand Corporation (Norand) 41. PCTEST Engineering Laboratory (PCTEST) 42. M. A. Plante 43. Retlif Testing Laboratories (Retlif) 44. Bruce Reynolds 45. Scientific-Atlanta (SA) 46. Silicon Graphics (SI) 47. Richard Smith 48. Sony Electronics (Sony) 49. Spirit Technologies (Spirit) 50. Sun Microsystems Computer Company (Sun) 51. Taipei Economic and Cultural Representative Office 52. Texas Instruments (TI) 53. Timco Engineering 54. Tokin 55. The Unisys Corporation (Unisys) 56. U. S. Department of Commerce 57. Washington Laboratories (WL) Parties Filing Reply Comments: 1. AT&T 2. Capital Cities/ABC 3. EIA/CEG 4. Gateway 5. HP 6. Howard Forman 7. ITI 8. Motorola 9. Richard Smith 10. Spirit 11. The Telecommunications Industry Association User Premises Equipment Division (TIA) 12. Vtech Computers, Inc. (Vtech) 13. Xerox APPENDIX C A. Title 47 of the Code of Federal Regulations, Part 0, is amended as follows: 1. The authority citation for Part 0 continues to read as follows: Authority: Secs. 5, 48 Stat. 1068, as amended; 47 U.S.C. 155. 2. Section 0.241 is amended by adding a new paragraph (f), to read as follows: Section 0.241 Authority delegated. * * * * * (f) The Chief of the Office of Engineering and Technology is authorized to enter into agreements with the National Institute of Standards and Technology and other accreditation bodies to perform accreditation of test laboratories pursuant to Section 2.948(d) of this chapter. In addition, the Chief is authorized to make determinations regarding the continued acceptability of individual accrediting organizations and accredited laboratories. B. Title 47 of the Code of Federal Regulations, Part 2, is amended as follows: 1. The authority citation for Part 2 continues to read as follows: Authority: Sec. 4, 302, 303, and 307 of the Communications Act of 1934, as amended, 47 U.S.C. Sections 154, 302, 303, and 307, unless otherwise noted. 2. Section 2.805 is revised to read as follows: Section 2.805 Equipment that does not require Commission approval. In the case of a radio frequency device that, in accordance with the rules in this chapter, does not have to have a grant of equipment authorization issued by the Commission, e.g., a device subject to verification or a Declaration of Conformity, but, nevertheless, must comply with specified technical standards prior to use, no person shall sell or lease, or offer for sale or lease (including advertising for sale or lease), or import, ship or distribute for the purposes of selling or leasing or offering for sale or lease, any such radio frequency device unless, prior thereto, such device complies with the applicable administrative and technical provisions (including verification or Declaration of Conformity of the equipment, where required) specified in the Commission's rules. 3. Section 2.901 is revised to read as follows: Section 2.901 Basis and purpose. (a) In order to carry out its responsibilities under the Communications Act and the various treaties and international regulations, and in order to promote efficient use of the radio spectrum, the Commission has developed technical standards for radio frequency equipment and parts or components thereof. The technical standards applicable to individual types of equipment are found in that part of the rules governing the service wherein the equipment is to be operated. In addition to the technical standards provided, the rules governing the service may require that such equipment be verified by the manufacturer or importer, be authorized under a Declaration of Conformity, or receive an equipment authorization from the Commission by one of the following procedures: type approval, type acceptance, certification, registration or notification. (b) The following sections describe the verification procedure, the procedure for a Declaration of Conformity, and the procedures to be followed in obtaining type approval, type acceptance, certification or notification from the Commission and the conditions attendant to such a grant. 4. A new Section 2.906 is added to read as follows: Section 2.906 Declaration of Conformity. (a) A Declaration of Conformity is a procedure where the responsible party, as defined in Section 2.909, makes measurements or takes other necessary steps to ensure that the equipment complies with the appropriate technical standards. Submittal of a sample unit or representative data to the Commission demonstrating compliance is not required unless specifically requested pursuant to Section 2.1076 of this part. (b) The Declaration of Conformity attaches to all items subsequently marketed by the responsible party which are identical, as defined in Section 2.908 of this part, to the sample tested and found acceptable by the responsible party. 5. Section 2.909 is amended by revising the introductory sentence and by adding a new paragraph (c), to read as follows: Section 2.909 Responsible party. The following parties are responsible for the compliance of radio frequency equipment with the applicable standards: * * * * * (c) In the case of equipment subject to authorization under the Declaration of Conformity procedure: (1) The manufacturer or, if the equipment is assembled from individual component parts and the resulting system is subject to authorization under a Declaration of Conformity, the assembler. (2) If the equipment, by itself, is subject to a Declaration of Conformity and that equipment is imported, the importer. 6. Section 2.913 is revised to read as follows: Section 2.913 Submittal of equipment authorization application or information to the Commission. (a) Unless otherwise directed, applications with fees attached for the equipment authorization, pursuant to Section 1.1103 of this chapter, must be submitted to the Federal Communications Commission, Equipment Approval Services, P. O. Box 358315, Pittsburgh, PA 15251-5315. If the applicant chooses to make use of an air courier/package delivery service, the following address must appear on the outside of the package/envelope: Federal Communications Commission, c/o Mellon Bank, Three Mellon Bank Center, 525 William Penn Way, 27th floor, Room 153-2713, Pittsburgh, Pennsylvania 15259- 0001, attention: Wholesale Lockbox Supervisor. (b) Any information or equipment samples requested by the Commission pursuant to the provisions of Subpart J of this part shall, unless otherwise directed, be submitted to the FCC, Equipment Authorization Division, 7434 Oakland Mills Road, Columbia, Maryland 21046. 7. The heading between Sections 2.926 and 2.927 is revised to read "Conditions Attendant to an Equipment Authorization." 8. Section 2.937 is revised to read as follows: Section 2.937 Equipment defect and/or design change. When a complaint is filed with the Commission concerning the failure of equipment subject to this chapter to comply with pertinent requirements of the Commission's rules, and the Commission determines that the complaint is justified and arises out of an equipment fault attributable to the responsible party, the Commission may require the responsible party to investigate such complaint and report the results of such investigation to the Commission. The report shall also indicate what action if any has been taken or is proposed to be taken by the responsible party to correct the defect, both in terms of future production and with reference to articles in the possession of users, sellers and distributors. 9. Section 2.945 is revised to read as follows: Section 2.945 Sampling tests of equipment compliance. The Commission will, from time to time, request the responsible party to submit equipment subject to this chapter to determine the extent to which subsequent production of such equipment continues to comply with the data filed by the applicant (or on file with the responsible party for equipment subject to notification or a Declaration of Conformity). Shipping costs to the Commission's laboratory and return shall be borne by the responsible party. 10. Section 2.946 is amended by revising paragraphs (a) and (b), to read as follows: Section 2.946 Penalty for failure to provide test samples and data. (a) Any responsible party, as defined in Section 2.909 of this chapter, or any party who markets equipment subject to the provisions of this chapter, shall provide test sample(s) or data upon request by the Commission. Failure to comply with such a request with the time frames shown below may be cause for forfeiture, pursuant to Section 1.80 of Part 1 of this chapter, or other administrative sanctions such as suspending action on any applications for equipment authorization submitted by such party while the matter is being resolved. (1) When the equipment is subject to authorization under a Declaration of Conformity, data shall be provided within 14 days of delivery of the request and test sample(s) shall be provided within 60 days of delivery of the request. (2) For all other devices, test sample(s) or data shall be provided within 60 days of the request. (b) In the case of equipment involving harmful interference or safety of life or property, the Commission may specify that test samples subject to the provisions of this section be submitted within less than 60 days, but not less than 14 days. Failure to comply within the specified time period will be subject to the sanctions specified in paragraph (a) of this section. * * * * * 11. Section 2.948 is amended by adding new paragraphs (a)(3) and (d), to read as follows: Section 2.948 Description of measurement facilities. (a) * * * * * * * * (3) If the equipment is to be authorized under a Declaration of Conformity, the description of the measurement facilities shall be retained by the party performing the measurements. * * * * * (d) If the equipment is to be authorized under a Declaration of Conformity, the party performing the measurements shall be accredited for performing such measurements by an authorized accreditation body based on the International Organization for Standardization/International Electrotechnical Commission (ISO/IEC) Guide 25, "General Requirements for the Competence of Calibration and Testing Laboratories." Accreditation bodies must be approved by the FCC's Office of Engineering and Technology, as indicated in Section 0.241 of this chapter, to perform such accreditation based on ISO/IEC 58, "Calibration and Testing Laboratory Accreditation Systems - General Requirements for Operation and Recognition." The frequency for revalidation of the test site and the information required to be filed or retained by the testing party shall comply with the requirements established by the accrediting organization. NOTE: Parties that are located outside of the United States or its possessions will be accredited only if there is a mutual recognition agreement between that country and the United States that permits similar accreditation of U.S. facilities to perform testing for products marketed in that country. 12. A new heading "DECLARATION OF CONFORMITY" is placed after Section 2.1065. 13. A new Section 2.1071 is added after the heading "DECLARATION OF CONFORMITY", to read as follows: Section 2.1071 Cross reference. The general provisions of this subpart, Section 2.901, et seq., shall apply to equipment subject to a Declaration of Conformity. 14. A new Section 2.1072 is added to read as follows: Section 2.1072 Limitation on Declaration of Conformity. (a) The Declaration of Conformity signifies that the responsible party, as defined in Section 2.909 of this part, has determined that the equipment has been shown to comply with the applicable technical standards if no unauthorized change is made in the equipment and if the equipment is properly maintained and operated. Compliance with these standards shall not be construed to be a finding by the responsible party with respect to matters not encompassed by the Commission's rules. (b) A Declaration of Conformity by the responsible party is effective until a termination date is otherwise established by the Commission. (c) No person shall, in any advertising matter, brochure, etc., use or make reference to a Declaration of Conformity in a deceptive or misleading manner or convey the impression that such a Declaration of Conformity reflects more than a determination by the responsible party that the device or product has been shown to be capable of complying with the applicable technical standards of the Commission's rules. 15. A new Section 2.1073 is added to read as follows: Section 2.1073 Responsibilities. (a) The responsible party, as defined in Section 2.909 of this part, must warrant that each unit of equipment marketed under a Declaration of Conformity is identical to the unit tested and found acceptable with the standards and that the records maintained by the responsible party continue to reflect the equipment being produced under the Declaration of Conformity within the variation that can be expected due to quantity production and testing on a statistical basis. (b) The responsible party, if different from the manufacturer, may upon receiving a written statement from the manufacturer that the equipment complies with the appropriate technical standards rely on the manufacturer or independent testing agency to determine compliance. However, the test records required by Section 2.1075 of this part shall be in the English language and shall be made available to the Commission upon a reasonable request in accordance with the provisions of Section 2.1076 of this part. (c) In the case of transfer of control of the equipment, as in the case of sale or merger of the responsible party, the new responsible party shall bear the responsibility of continued compliance of the equipment. (d) Equipment shall be retested to demonstrate continued compliance with the applicable technical standards if any modifications or changes that could adversely affect the emanation characteristics of the equipment are made by the responsible party. The responsible party bears responsibility for the continued compliance of subsequently produced equipment. (e) If any modifications or changes are made by anyone other than the responsible party for the Declaration of Conformity, the party making the modifications or changes, if located within the U.S., becomes the new responsible party. The new responsible party must comply with all provisions for the Declaration of Conformity, including having test data on file demonstrating that the product continues to comply with all of the applicable technical standards. 16. A new Section 2.1074 is added to read as follows: Section 2.1074 Identification. Devices subject only to a Declaration of Conformity shall be uniquely identified by the responsible party. This identification shall not be of a format which could be confused with the FCC Identifier required on certified, notified, type accepted or type approved equipment. The responsible party shall maintain adequate identification records to facilitate positive identification for each device. 17. A new Section 2.1075 is added to read as follows: Section 2.1075 Retention of records. (a) Except as shown in paragraph (b) of this section, for each product subject to a Declaration of Conformity, the responsible party, as shown in Section 2.909 of this part, shall maintain the records listed below: (1) A record of the original design drawings and specifications and all changes that have been made that may affect compliance with the requirements of Section 2.1073 of this part. (2) A record of the procedures used for production inspection and testing (if tests were performed) to insure the conformance required by Section 2.1073 of this part. (Statistical production line emission testing is not required.) (3) A record of the measurements made on an appropriate test site that demonstrates compliance with the applicable regulations. The record shall contain: (i) The actual date or dates testing was performed. (ii) The name of the test laboratory, company, or individual performing the testing. The Commission may request additional information regarding the test site, the test equipment or the qualifications of the company or individual performing the tests. (iii) A description of how the device was actually tested, identifying the measurement procedure and test equipment that was used. (iv) A description of the equipment under test (EUT) and support equipment connected to, or installed within, the EUT. (v) The identification of the EUT and support equipment by trade name and model number and, if appropriate, by FCC Identifier and serial number. (vi) The types and lengths of connecting cables used and how they were arranged or moved during testing. (vii) At least two photographs showing the test set-up for the highest line conducted emission and showing the test set-up for the highest radiated emission. These photographs must be focused originals which show enough detail to confirm other information contained in the test report. (viii) A description of any modifications made to the EUT by the testing company or individual to achieve compliance with the regulations. (ix) All of the data required to show compliance with the appropriate regulations. (x) The signature of the individual responsible for testing the product along with the name and signature of an official of the responsible party, as designated in Section 2.909 of this part. (xi) A copy of the compliance information, as described in Section 2.1077 of this chapter, required to be provided with the equipment. (b) If the equipment is assembled using modular components that, by themselves, are subject to authorization under a Declaration of Conformity and/or a grant of certification, and the assembled product is also subject to authorization under a Declaration of Conformity but, in accordance with the applicable regulations, does not require additional testing, the assembler shall maintain the records listed below in order to show the basis on which compliance with the standards was determined: (1) A listing of all of the components used in the assembly. (2) Copies of the compliance information, as described in Section 2.1077 of this chapter, for all of the modular components used in the assembly. (3) A listing of the FCC Identifier numbers for all of the components used in the assembly that are authorized under a grant of certification. (4) A listing of equipment modifications, if any, that were made during assembly. (5) A copy of any instructions included with the components that were required to be followed to ensure the assembly of a compliant product, along with a statement, signed by the assembler, that these instructions were followed during assembly. This statement shall also contain the name and signature of an official of the responsible party, as designated in Section 2.909 of this part. (c) The records listed in paragraphs (a) and (b) of this section shall be retained for two years after the manufacture or assembly, as appropriate, of said equipment has been permanently discontinued, or until the conclusion of an investigation or a proceeding if the responsible party is officially notified that an investigation or any other administrative proceeding involving the equipment has been instituted. Requests for the records described in this section and for sample units also are covered under the provisions of Section 2.946 of this part. 18. A new Section 2.1076 is added to read as follows: Section 2.1076 FCC inspection and submission of equipment for testing. (a) Each responsible party, upon receipt of a reasonable request, shall submit to the Commission the records required by Section 2.1075 of this part or one or more sample units for measurements at the Commission's laboratory. (b) Shipping costs to the Commission's Laboratory and return shall be borne by the responsible party. In the event the responsible party believes that shipment of the sample to the Commission's Laboratory is impractical because of the size or weight of the equipment, or the power requirement, or for any other reason, the responsible party may submit a written explanation why such shipment is impractical and should not be required. 19. A new Section 2.1077 is added to read as follows: Section 2.1077 Compliance information. (a) If a product must be tested and authorized under a Declaration of Conformity, a compliance information statement shall be supplied with the product at the time of marketing or importation, containing the following information: (1) Identification of the product, e.g., name and model number. (2) A statement, similar to that contained in Section 15.19(a)(3) of this chapter, that the product complies with Part 15 of the regulations. (3) The identification, by name, address and telephone number, of the responsible party, as defined in Section 2.909 of this chapter. The responsible party for a Declaration of Conformity must be located within the United States. (b) If a product is assembled from modular components that, by themselves, are authorized under a Declaration of Conformity and/or a grant of certification, and the assembled product is also subject to authorization under a Declaration of Conformity but, in accordance with the applicable regulations, does not require additional testing, the product shall be supplied, at the time of marketing or importation, with a compliance information statement containing the following information: (1) Identification of the modular components used in the assembly. A modular component authorized under a Declaration of Conformity shall be identified as specified in paragraph (a)(1) of this section. A modular component authorized under a grant of certification shall be identified by name and model number (if applicable) along with the FCC Identifier number. (2) A statement that the product complies with Part 15 of the regulations. (3) The identification, by name, address and telephone number, of the responsible party who assembled the product from modular components, as defined in Section 2.909 of this chapter. The responsible party for a Declaration of Conformity must be located within the United States. (4) Copies of the compliance information statements for each modular component used in the system that is authorized under a Declaration of Conformity. (c) The compliance information statement shall be included in the user's manual or as a separate sheet. C. Title 47 of the Code of Federal Regulations, Part 15, is amended as follows: 1. The authority citation for Part 15 continues to read as follows: Authority: Sec. 4, 302, 303, 304, and 307 of the Communications Act of 1934, as amended, 47 U.S.C. Sections 154, 302, 303, 304, and 307. 2. Section 15.3 is amended by revising paragraph (r) and adding a new paragraph (bb), to read as follows: Section 15.3 Definitions. * * * * * (r) Peripheral device. An input/output unit of a system that feeds data into and/or receives data from the central processing unit of a digital device. Peripherals to a digital device include any device that is connected external to the digital device, any device internal to the digital device that connects the digital device to an external device by wire or cable, and any circuit board designed for interchangeable mounting, internally or externally, that increases the operating or processing speed of a digital device, e.g., "turbo" cards and "enhancement" boards. Examples of peripheral devices include terminals, printers, external floppy disk drives and other data storage devices, video monitors, keyboards, interface boards, external memory expansion cards, and other input/output devices that may or may not contain digital circuitry. This definition does not include CPU boards, as defined in paragraph (bb) of this section, even though a CPU board may connect to an external keyboard or other components. * * * * * (bb) CPU board. A circuit board that contains a microprocessor, or frequency determining circuitry for the microprocessor, the primary function of which is to execute user-provided programming, but not including: (1) a circuit board that contains only a microprocessor intended to operate under the primary control or instruction of a microprocessor external to such a circuit board; or, (2) a circuit board that is a dedicated controller for a storage or input/output device. 3. Section 15.19 is amended by redesignating paragraph (b) as paragraph (a)(4), by redesignating paragraph (c) as paragraph (a)(5), by revising paragraphs (a)(4) and (a)(5), and by adding new paragraphs (b) and (c), to read as follows: Section 15.19 Labelling requirements. (a) * * * * * * * * (4) Where a device is constructed in two or more sections connected by wires and marketed together, the statement specified under paragraph (a) of this section is required to be affixed only to the main control unit. (5) When the device is so small or for such use that it is not practicable to place the statement specified under paragraph (a) of this section on it, the information required by this paragraph shall be placed in a prominent location in the instruction manual or pamphlet supplied to the user or, alternatively, shall be placed on the container in which the device is marketed. However, the FCC identifier or the unique identifier, as appropriate, must be displayed on the device. (b) Products subject to authorization under a Declaration of Conformity shall be labelled as follows: (1) The label shall be located in a conspicuous location on the device and shall contain the unique identification described in Section 2.1074 of this chapter and the following logo: (i) If the product is authorized based on testing of the product or system: (ii) If the product is authorized based on assembly using separately authorized components and the resulting product is not separately tested: (2) When the device is so small or for such use that it is not practicable to place the statement specified under paragraph (b)(1) of this section on it, such as for a CPU board or a plug-in circuit board peripheral device, the text associated with the logo may be placed in a prominent location in the instruction manual or pamphlet supplied to the user. However, the unique identification (trade name and model number) and the logo must be displayed on the device. (3) The label shall not be a stick-on, paper label. The label on these products shall be permanently affixed to the product and shall be readily visible to the purchaser at the time of purchase, as described in Section 2.925(d) of this chapter. "Permanently affixed" means that the label is etched, engraved, stamped, silkscreened, indelibly printed, or otherwise permanently marked on a permanently attached part of the equipment or on a nameplate of metal, plastic, or other material fastened to the equipment by welding, riveting, or a permanent adhesive. The label must be designed to last the expected lifetime of the equipment in the environment in which the equipment may be operated and must not be readily detachable. (c) [reserved] * * * * * 4. A new Section 15.32 is added, to read as follows: Section 15.32 Test procedures for CPU boards and computer power supplies. Power supplies and CPU boards used with personal computers and for which separate authorizations are required to be obtained shall be tested as follows: (a) CPU boards shall be tested as follows: (1) Testing for radiated emissions shall be performed with the CPU board installed in a typical enclosure but with the enclosure's cover removed so that the internal circuitry is exposed at the top and on at least two sides. Additional components, including a power supply, peripheral devices, and subassemblies, shall be added, as needed, to result in a complete personal computer system. If the oscillator and the microprocessor circuits are contained on separate circuit boards, both boards, typical of the combination that would normally be employed, must be used in the test. Testing shall be in accordance with the procedures specified in Section 15.31 of this part. Under these test conditions, the system under test shall not exceed the radiated emission limits specified in Section 15.109 of this part by more than 3 dB. (2) Unless the test in paragraph (a)(1) of this section demonstrates compliance with the limits in Section 15.109 of this part, a second test shall be performed using the same configuration described above but with the cover installed on the enclosure. Testing shall be in accordance with the procedures specified in Section 15.31 of this part. Under these test conditions, the system under test shall not exceed the radiated emission limits specified in Section 15.109 of this part. (3) The test demonstrating compliance with the AC power line conducted limits specified in Section 15.107 of this part shall be performed in accordance with the procedures specified in Section 15.31 using a enclosure, peripherals, power supply and subassemblies that are typical of the type with which the CPU board under test would normally be employed. (b) The power supply shall be tested installed in an enclosure that is typical of the type within which it would normally be installed. Additional components, including peripheral devices, a CPU board, and subassemblies, shall be added, as needed, to result in a complete personal computer system. Testing shall be in accordance with the procedures specified in Section 15.31 and must demonstrate compliance with all of the standards contained in this part. 5. Section 15.37 is amended by adding a new paragraph (g), to read as follows: Section 15.37 Transition provisions for compliance with the rules. * * * * * (g) For CPU boards and power supplies designed to be used with personal computers: The manufacture and importation of these products shall cease on or before [insert date 12 months after date of publication in the Federal Register] unless these products have been authorized under a Declaration of Conformity or a grant of certification, demonstrating compliance with all of the provisions in this Part. Limited provisions, as detailed in Section 15.101(d) of this Chapter, are provided to permit the importation and manufacture of these products subsequent to this date where the CPU boards and/or power supplies are marketed only to personal computer equipment manufacturers. 6. Section 15.101 is amended by revising the table in paragraph (a) and the text of paragraphs (c), (d), (e), and (f), to read as follows: Section 15.101 Equipment authorization of unintentional radiators. (a) * * * Type of Device ,Equipment Authorization Required TV broadcast receiver.............................. FM broadcast receiver............................. CB receiver.............................................. Superregenerative receiver....................... Scanning receiver..................................... All other receivers subject to Part 15..... TV interface device.................................. Cable system terminal device.................. Stand-alone cable input selector switch.. Class B personal computers and peripherals............................................ CPU boards and power supplies used with Class B personal computers......... Class B personal computers assembled using authorized CPU boards or power supplies....................................... Class B external switching power supplies not used with personal computers............................................... Other Class B digital devices & peripherals.............................................. Class A digital devices, peripherals & external switching power supplies........ All other devices...................................... ,Verification Verification Certification Certification Certification Notification Certification Notification Verification Declaration of Conformity or Certification Declaration of Conformity or Certification Declaration of Conformity Verification Verification Verification Verification (b) * * * (c) Personal computers shall be authorized in accordance with one of the following methods: (1) The specific combination of CPU board, power supply and enclosure is tested together and authorized under a Declaration of Conformity or a grant of certification; (2) The personal computer is authorized under a Declaration of Conformity or a grant of certification, and the CPU board or power supply in that computer is replaced with a CPU board or power supply that has been separately authorized under a Declaration of Conformity or a grant of certification; or, (3) The CPU board and power supply used in the assembly of a personal computer have been separately authorized under a Declaration of Conformity or a grant of certification. (4) Personal computers assembled using either of the methods specified in paragraphs (c)(2) or (c)(3) of this section must, by themselves, also be authorized under a Declaration of Conformity if they are marketed. However, additional testing is not required for this Declaration of Conformity, provided the procedures in Section 15.102(b) of this chapter are followed. (d) Peripheral devices, as defined in Section 15.3(r), shall be authorized under a Declaration of Conformity, or a grant of certification, or verified, as appropriate, prior to marketing. Regardless of the provisions of paragraphs (a) or (c) of this section, if a CPU board, power supply, or peripheral device will always be marketed with a specific personal computer, it is not necessary to obtain a separate authorization for that product provided the specific combination of personal computer, peripheral device, CPU board and power supply has been authorized under a Declaration of Conformity or a grant of certification as a personal computer. (1) No authorization is required for a peripheral device or a subassembly that is sold to an equipment manufacturer for further fabrication; that manufacturer is responsible for obtaining the necessary authorization prior to further marketing to a vendor or to a user. (2) Power supplies and CPU boards that have not been separately authorized and are designed for use with personal computers may be imported and marketed only to a personal computer equipment manufacturer that has indicated, in writing, to the seller or importer that they will obtain a Declaration of Conformity or a grant of certification for the personal computer employing these components. (e) Subassemblies to digital devices are not subject to the technical standards in this part unless they are marketed as part of a system in which case the resulting system must comply with the applicable regulations. Subassemblies include: (1) Devices that are enclosed solely within the enclosure housing the digital device, except for: power supplies used in personal computers; devices included under the definition of a peripheral device in Section 15.3(r); and personal computer CPU boards, as defined in Section 15.3(bb); (2) CPU boards, as defined in Section 15.3(bb), other than those used in personal computers, that are marketed without an enclosure or power supply; and, (3) Switching power supplies that are separately marketed and are solely for use internal to a device other than a personal computer. (f) The procedures for obtaining a grant of certification or notification and for verification and a Declaration of Conformity are contained in Subpart J of Part 2 of this chapter. 7. A new Section 15.102 is added to read as follows: Section 15.102 CPU boards and power supplies used in personal computers. (a) Authorized CPU boards and power supplies that are sold as separate components shall be supplied with complete installation instructions. These instructions shall specify all of the installation procedures that must be followed to ensure compliance with the standards, including, if necessary, the type of enclosure, e.g., a metal enclosure, proper grounding techniques, the use of shielded cables, the addition of any needed components, and any necessary modifications to additional components. (1) Any additional parts needed to ensure compliance with the standards, except for the enclosure, are considered to be special accessories and, in accordance with Section 15.27 of this part, must be marketed with the CPU board or power supply. (2) Any modifications that must be made to a personal computer, peripheral device, CPU board or power supply during installation of a CPU board or power supply must be simple enough that they can be performed by the average consumer. Parts requiring soldering, disassembly of circuitry or other similar modifications are not permitted. (b) Assemblers of personal computer systems employing modular CPU boards and/or power supplies are not required to test the resulting system provided the following conditions are met: (1) Each device used in the system has been authorized as required under this part (Note: according to Section 15.101(e), some subassemblies used in a personal computer system may not require an authorization); (2) The original label and identification on each piece of equipment remain unchanged; (3) Each responsible party's instructions to ensure compliance (including, if necessary, the use of shielded cables or other accessories or modifications) are followed when the system is assembled; and, (4) If the system is marketed, the resulting equipment combination is authorized under a Declaration of Conformity pursuant to Section 15.101(c)(4) of this part and a compliance information statement, as described in Section 2.1077(b) of this chapter, is supplied with the system. Marketed systems shall also comply with the labelling requirements in Section 15.19 of this part and must be supplied with the information required under Sections 15.21, 15.27 and 15.105 of this part. (5) The assembler of a personal computer system may be required to test the system and/or make necessary modifications if a system is found to cause harmful interference or to be noncompliant with the appropriate standards in the configuration in which it is marketed (see Sections 2.909, 15.1, 15.27(d) and 15.101(e) of this Chapter).